Micro Summary: How long does 3D laser scanning a mine or processing plant take? Innosa Projects explains scan timelines for different mine site types.
Micro Summary
“A single mine building or conveyor system takes one shift (8–12 hours) to scan. A full processing plant complex takes two to three shifts. Innosa Projects delivers point clouds and as-built drawings within 5–7 business days of scan completion.”
How long does 3D scanning a mine take? The honest answer depends on the size and complexity of what is being scanned. Here is a practical guide to scan timelines based on Innosa Projects’ experience scanning mine sites across the North West Platinum Belt.
Typical Scan Timelines by Scope.
Single building or processing area (up to 2,000m²). One shift, 8 to 12 hours on site including setup, scanning, and quality verification.
Conveyor system (single line, surface). Half to one shift, 4 to 8 hours depending on length and access complexity.
Full processing plant (multiple buildings, pipe bridges, tank farm). Two to three days typically 16 to 24 hours of on-site scanning.
Underground workings (haulage levels, shaft infrastructure). One to two shifts per level, depending on drive length and access.
What happens after the scan?
Generally there are 4 main steps:
- The actual 3D Scanning
- Scan registration, noise removal. This can be delivered as ‘raw’ pointcloud
Data, such as E57, .LAS, .PTS,
- The point cloud can then be developed into usable Engineering, Structural and Architectural 3D models used for CAD packages such as Revit, AutoCad, etc
- In addition, 2D as-built drawings can also be developed with the desired level of detailing and supplied as DWG, .DXF and .DGN
Can the timeline be compressed for Shutdown Deadlines?
Yes. Innosa Projects regularly works to compress timelines for clients with fixed shutdown windows. If you have a specific delivery deadline. For example, scan data needed before a shutdown that opens in two weeks. Call +27 81 445 3066 or email info@innosaprojects.co.za. We’re based in Rustenburg, mobilise across Gauteng, and KwaZulu-Natal, and work nationally across South Africa.
We will confirm whether the timeline is achievable. For Platinum Belt operations in Rustenburg and North West Province, Innosa can mobilise within 24–48 hours of a confirmed scope and access approval.
Related questions
Read the full guide here:
How Innosa Projects scans active mines without stopping production.